Update: Major Works
- Strata Secretary

- Aug 7, 2024
- 1 min read

The contractor carrying out the major works has reported that the demolition is going well. In most cases the tiles are coming up fairly readily. At this stage he anticipates that the noisy demolition work will be completed by the end of next week. That will be followed by a period of intermittent noise before the completion of all the drilling/jackhammering and the quieter waterproofing and tiling commences.
Don't forget about the information session on Thursday 8 August at 5pm. There's a separate post on that session which includes a link to join in Microsoft Teams.